Michael Crim

Millersville, Maryland, United States
8K followers 500+ connections

Join to view profile

About

Mike has over 20 years of experience in the commercial construction industry. He has a…

Activity

Join now to see all activity

Experience & Education

  • CK Commercial

View Michael’s full experience

See their title, tenure and more.

or

By clicking Continue to join or sign in, you agree to LinkedIn’s User Agreement, Privacy Policy, and Cookie Policy.

Licenses & Certifications

  • Construction Quality Management Certificate

    US Army Corps of Engineers

  • First Aid / CPR

    -

  • OSHA 30 Hour

    -

Volunteer Experience

  • AACC Foundation Graphic

    Board Member

    AACC Foundation

    - 2 years 9 months

    Education

    The Foundation’s mission is to expand private philanthropy and cultivate partnerships to enhance AACC’s ability to support students and initiatives that strengthen our community. Our success would not be possible without the generosity of our donors. It is with this dedication and support that Anne Arundel Community College is able to provide more solutions that make our community stronger.

Projects

  • Project 100.5

    -

    SCOPE: $6.4 Million| 58,821 SF High-tech Interior Build-out | 20 week schedule

    The 58,821 Square Foot, state-of-the-art facility that houses 250 professionals. The project included 3 self-sustaining laboratories with over 120 total racks and individual electrical metering, raised access flooring, complete power back-up for each laboratory, main building switch gear upgrade, training and conference rooms, administrative space, three separate IT communications networks and associated…

    SCOPE: $6.4 Million| 58,821 SF High-tech Interior Build-out | 20 week schedule

    The 58,821 Square Foot, state-of-the-art facility that houses 250 professionals. The project included 3 self-sustaining laboratories with over 120 total racks and individual electrical metering, raised access flooring, complete power back-up for each laboratory, main building switch gear upgrade, training and conference rooms, administrative space, three separate IT communications networks and associated cabling, and an Advanced Innovation Center that included high-end architectural components and a complex standalone Audio Visual integration system. The projected achieved LEED GOLD CERTIFICATION.

  • Project 100.9

    -

    SCOPE: $10 Million | 14,960 SF Class 100,000 Clean Room | 12 week schedule

    Class 100,000 Clean Room Lab project for an undisclosed prominent DoD Contractor was in support of their cyber security division program and built to Secure Space Construction ICD 705 Standards. Project included; Laser Lab Clean Room, Four (4) Labs and One (1) Staging Area with static-control resilient raised access floors, metal laboratory casework with chem-resin countertops, and metal sound control doors. The…

    SCOPE: $10 Million | 14,960 SF Class 100,000 Clean Room | 12 week schedule

    Class 100,000 Clean Room Lab project for an undisclosed prominent DoD Contractor was in support of their cyber security division program and built to Secure Space Construction ICD 705 Standards. Project included; Laser Lab Clean Room, Four (4) Labs and One (1) Staging Area with static-control resilient raised access floors, metal laboratory casework with chem-resin countertops, and metal sound control doors. The detailed project scope included: Full demolition of all interior infrastructure, removal of all technical MEP Systems, and select exterior demolition of an existing 15,000 SF high bay building; 35 tons of metal was recycled.
    Concrete work included 64 individual vibration isolation piers to accommodate 16 vibration isolation tables - New HVAC System included 50,000 lbs. of sheet metal and over 1 mile of ductwork installed - Specialty Mechanical and Plumbing Systems with Vibration and Seismic Controls for HVAC Piping and Equipment included a Dedicated Outdoor Air System and (5) large Air Handling Units to serve the labs and staging area with laminar flow accommodating stringent temperature and humidity controls
    Project also included a Processed Chilled Water System including Reverse Osmosis (RO) water filter system with a chemical injection pump and Deionized (DI) water system - High Efficiency Condensing Type Boiler System - Dust Collection Systems - Compressed-Air System - Vacuum System - Vacuum Ovens, Laboratory chemical fume hood - Fully integrated Building Automation & Thermal Energy Control System - Fire Protection Systems included new wet pipe system and dry pipe system in lab areas. Electrical, Tele-data, and Audio Visual Systems included 8,900 lineal feet of color coordinated conduit runs, Electrical service upgrade to obtain 1.5 megawatts of electrical power, 21,000 lineal feet of electrical cabling.

More activity by Michael

View Michael’s full profile

  • See who you know in common
  • Get introduced
  • Contact Michael directly
Join to view full profile

Other similar profiles

Explore top content on LinkedIn

Find curated posts and insights for relevant topics all in one place.

View top content